Project Overview
Location: Texas
Facility Type: Data Center
Project Date: June 2025
Services Provided:
- Data Center Services
- Data Center Decommissioning
- Data Center Equipment Supply & Installation
- Critical System Disconnects (UPS, PDU, HVAC)
- Data Center Decommissioning
- Decommissioning & Asset Recovery
- Generator Decommissioning
- Electrical & Mechanical Asset Recovery for Resale
- Rigging & Tower Services
- Heavy Equipment Rigging & Relocation
- Critical Equipment Shipping & Handling
- Heavy Equipment Rigging & Relocation
- General Contracting
- End-to-end Project Management & Coordination
- Construction Schedule & Logistics Oversight
Project Scope
- Emergency replacement of a failed 1 MW standby generator
- Decommissioning and removal of existing 1 MW Detroit Diesel generator
- Procurement, delivery, installation, and commissioning of new 1 MW Cummins generator
- Rigging, logistics coordination, and site restoration
- Full compliance verification and commissioning documentation
The Challenge
The project began as an emergency response after a standby generator experienced an arc flash and could no longer be trusted to operate reliably. Because the site is a live colocation data center, the client required immediate action with zero tolerance for downtime.
Time was the primary constraint. The facility needed a like-for-like replacement sourced, mobilized, installed, and commissioned within days — not weeks — while maintaining full operational integrity of the site.
Our Solution
Within two days of inquiry, Travel Safe mobilized a specialized critical power and rigging team to site. We first safely decommissioned and removed the compromised 1 MW Detroit Diesel generator, coordinating disconnects, rigging, and off-site transport.
In parallel, we sourced a replacement 1 MW Cummins generator, managed expedited logistics, and prepared the site for installation. Our crews self-performed all rigging, electrical tie-ins, testing, and commissioning, ensuring seamless integration with existing infrastructure.
A dedicated account manager and onsite project manager maintained continuous coordination with the facility’s leadership team, providing real-time updates and maintaining strict safety and compliance protocols throughout execution.
Results
- Decommissioned, removed, sourced, installed, and commissioned a replacement generator in 6 days total
- Delivered $584,000 in savings compared to the next most affordable contractor bid for the emergency generator scope.
- Completed all work with zero operational disruption
- Restored reliable standby power ahead of client expectations
